Major Performance

  • Korea Garakdong Electric Power Transmission Line

    • Period 2004.12 ~ 2009.11
    • Client Korea Electric Power Corporation
    • Location Seoul, Republic of Korea
    • Explanation EPB, LENGTH : 2,459(M)
      DIAMETER : 3,800(mm)
      Ground : Soft & Hard rock

      Equipment manufacturer : KAWASAWI Φ4550mm, JAPAN
  • Korea Incheon Airport Railroad Phase 2-5B

    • Period 2004.06 ~ 2008.08
    • Client Incheon International Airport Corporation
    • Location Incheon, Republic of Korea
    • Explanation EPB
      LENGTH-1,935(M)
      DIAMETER-6,880(mm)
      GROUND : weathering soil, Soft & Hard rock
  • Korea Busan Seomyean 1st Apartment Project

    • Period 2004.06 ~ 2007.02
    • Client Namkwang E&C
    • Location Busan, Republic of Korea
    • Explanation G/W Length : 643 m
      Thickness : 800 mm ~ 1200 mm
      Depth : 30.0 m
  • Korea Seoul-Busan Train Express Railway C14-2 / Tunnel Work

    • Period 2004.05 ~ 2010.03
    • Client Korea Train Express
    • Location Busan, Republic of Korea
    • Explanation Sectional area : 140m2
      Extended Length : 8,324m
      Rock Type : Hard Rock
  • Korea Seoul Metro Line 9 No.909

    • Period 2003.09 ~ 2009.12
    • Client Public Procurement Service
    • Location Seoul, Republic of Korea
    • Explanation Slurry : Length-3,634(M), Diameter-7,800(mm)
      Ground : Complex Stratum
  • Singapore DTSS-Kim Chuan Link sewer

    • Period 2002.05 ~ 2006.12
    • Client Singapore PUB
    • Location Singapore
    • Explanation Diameter 1,000(mm), Length 990m