Major Performance
-
Korea Construction of Road Between Busan-Geoje / immersed tunnel DCM
-
Period
2006.03 ~ 2008.12
-
Client
Busan-Geoje Fixed Link Corporation
-
Location
Busan, Geoje Gyeongsangnam-do, Republic of Korea
-
Explanation
Length : 128,292(m), 4 drivers
-
Korea Jeunggwan Industrial Complex Access Road Phase 1 Tunnel Work
-
Period
2005.12 ~ 2010.02
-
Client
Busan Infrastructure Headquarters
-
Location
Busan, Republic of Korea
-
Explanation
Sectional area : 81m2
Extended Length : 3,435m
Rock Type : Soft/Hard Rock
-
Korea Jeunggwan Industrial Complex Access Road Phase 2 Tunnel Work
-
Period
2005.12 ~ 2009.05
-
Client
Busan Infrastructure Headquarters
-
Location
Busan, Republic of Korea
-
Explanation
Sectional area : 81m2
Extended Length : 1,455m
Rock Type : Soft/Hard Rock
-
Korea Gyungeui Railway Line Double-Track Electrification Phase 2
-
Period
2005.11 ~ 2010.03
-
Client
Seoul Metropolitan Infrastructure Headquarters
-
Location
Seoul, Republic of Korea
-
Explanation
Sectional area : 85m2
Extended Length : 719m
Rock Type : Soft Rock
-
Korea Centum Reader’s Mark Building Project
-
Period
2005.10 ~ 2008.06
-
Client
Milestone D&C
-
Location
Busan, Republic of Korea
-
Explanation
Diaphragm Wall
-
Korea Ulsan New Port South Breakwater & other facility construction
-
Period
2005.07 ~ 2007.02
-
Client
Ulsan Regional Maritime Affairs and Port Administration
-
Location
Ulsan, Republic of Korea
-
Explanation
Length : 146,800(m), 4 drivers