Major Performance
-
Korea Intigraged Sewage facility Construction in Water resource Protection Area
-
Period
2010.06 ~ 2015.09
-
Client
Busan-si
-
Location
Busan, Republic Of Korea
-
Explanation
Sewer
-
Korea Halla Printing Valley
-
Period
2010.05 ~ 2013.11
-
Client
SJ Holdings Co., Ltd.
-
Location
Busan, Republic of Korea
-
Explanation
Earthwork, D-Wall, Bored Pile
-
Korea Gyeongju-si Expansion of Drainage system Project
-
Period
2010.04 ~ 2014.12
-
Client
Gyeongju Environment Corporation
-
Location
Gyeongju, Gyeongsangbuk-do, Republic of Korea
-
Explanation
Sewer
-
Korea Ulsan~Pohang Phase 5
-
Period
2010.03 ~ 2014.03
-
Client
Korea Expressway Corporation
-
Location
Yeongdeok, Gyeongsangbuk-do, Republic of Korea
-
Explanation
Bored Pile
-
Korea The Bank of Korea Busan Office
-
Period
2010.02 ~ 2013.09
-
Client
The Bank of Korea
-
Location
Busan, Republic of Korea
-
Explanation
Earthwork, Retaining of earth
-
Singapore DOWNTOWN LINE STAGE2 CONTRACT 913(SHIELD)
-
Period
2010.02 ~ 2013.12
-
Client
LTA
-
Location
Singapore
-
Explanation
Shield Tunnel